Javys, a.s.

Plan of V1 NPP Decommissioning

Projects are divided into three basic groups:

A. Projects related with enclosure of operation of V1 NPP

  • Development of complex documentation necessary for licensing phase of V1 NPP decommissioning and for phase of decommissioning performance
  • System of documentation management
  • Reconstruction of security system of locality of power plant AKOBOJE
  • Reconstruction of system of warning and notifying the public
  • Relocation of Center of Emergency Response
  • Assurance of suitable decontamination facilities
  • Change (separation) of feeding system of NPPs V1 and V2
  • Change of system of heat and steam supply
  • Reliable heat and steam supply: reconstruction of auxiliary boiler room in locality Bohunice
  • Modification of systems of cooling and technical water and system of natural input water
  • Replacement of operational media for NPPs V1 a V2
  • Treatment of spent fuel

B. Projects of documentation necessary for decommissioning

  • Conceptual plan of V1 NPP decommissioning
  • Report on evaluation of influence of NPP V1 decommissioning on environment
  • Plan of the first stage of V1 NPP decommissioning and other documentation
  • Decommissioning database

C. Projects related with treatment of radioactive waste

  • Processing of metallic waste
  • Processing of inherited waste, sludges of asorbents
  • Processing and treatment of inherited waste
  • Means of transport for transportation of inherited liquid RAW from V1 NPP to existing processing lines
  • Supply of transportation container for concentrates
  • Sampling, analysis and characterization of ion exchangers
  • Sampling, analysis and characterization of Ra sediments in storage basins
  • Integral storage of RAW in locality Bohunice
  • Enlargement of CS RAW Mochovce
  • Study of feasibility of enlargement of CS RAW Mochovce
  • Release of decommissioning materials
  • Storage of very low active RAW
  • Modernization of monitoring facility of radiation protection
detail