Feasibilty study of Treatment of Metallic waste & Procurement of portable fragmentation and decontamination equipment for metallic and building materials
Project identification: C7-A1
Project nameFeasibilty study of Treatment of Metallic waste & Procurement of portable fragmentation and decontamination equipment for metallic and building materials
project statusFinished
DescriptionObjectives: to establish the needs of Bohunice site to be able to carry out fragmentation and decontamination at two different stages: pre-dismantling and dismantling.
The activities corresponding to the pre-dismantling stage consist of changes and improvements to the existing Plant equipment. The activities corresponding to phase 2 of the project include the construction of installations and the purchase of new fragmentation and decontamination equipment.