Description

The purpose of the project D1.1 is dismantling, sorting, compacting, packaging, transport and disposal of thermal insulation materials from the technological systems and equipment of building No. 490 (V1 NPP turbine hall) and buildings No. 800/b and 800/c, floor +14.7 m (lengthwise intermediate buildings). The dismantling involves the thermal insulation of technological components, piping and tanks. The thermal insulation covers all technological equipment with an operational temperature over 50 °C to prevent staff injuries and reduce heat power loss. Covers of TG, “autobus” are also included. The materials in question predominantly include insulation (approx. 670 Te) based on glass/basaltic fibers and metallic material (some 161 Te).