Projects are divided into three basic groups:
A. Projects related with enclosure of operation of V1 NPP
- Development of complex documentation necessary for licensing phase of V1 NPP decommissioning and for phase of decommissioning performance
- System of documentation management
- Reconstruction of security system of locality of power plant AKOBOJE
- Reconstruction of system of warning and notifying the public
- Relocation of Center of Emergency Response
- Assurance of suitable decontamination facilities
- Change (separation) of feeding system of NPPs V1 and V2
- Change of system of heat and steam supply
- Reliable heat and steam supply: reconstruction of auxiliary boiler room in locality Bohunice
- Modification of systems of cooling and technical water and system of natural input water
- Replacement of operational media for NPPs V1 a V2
- Treatment of spent fuel
B. Projects of documentation necessary for decommissioning
- Conceptual plan of V1 NPP decommissioning
- Report on evaluation of influence of NPP V1 decommissioning on environment
- Plan of the first stage of V1 NPP decommissioning and other documentation
- Decommissioning database
C. Projects related with treatment of radioactive waste
- Processing of metallic waste
- Processing of inherited waste, sludges of asorbents
- Processing and treatment of inherited waste
- Means of transport for transportation of inherited liquid RAW from V1 NPP to existing processing lines
- Supply of transportation container for concentrates
- Sampling, analysis and characterization of ion exchangers
- Sampling, analysis and characterization of Ra sediments in storage basins
- Integral storage of RAW in locality Bohunice
- Enlargement of CS RAW Mochovce
- Study of feasibility of enlargement of CS RAW Mochovce
- Release of decommissioning materials
- Storage of very low active RAW
- Modernization of monitoring facility of radiation protection