24th April 1972 |
beginning of the construction of the V1 NPP |
7th November 1978 |
beginning of the insertion of nuclear fuel into the Unit 1 reactor |
27th November 1978 |
minimal controlled power reached at the Unit 1 reactor |
17th December 1978 |
Unit 1 enters testing operation |
15th March 1980 |
minimal controlled power reached at the Unit 2 reactor |
26th March 1980 |
Unit 2 enters testing operation |
1991 |
beginning of the small reconstruction |
1993 |
completion of the small reconstruction |
April 1996 |
beginning of the gradual reconstruction |
September 1999 |
the SR government decides to shut the V1 NPP down |
June 2000 |
completion of the gradual reconstruction |
31st December 2006 |
shutdown of Unit 1 |
31st December 2008 |
shutdown of Unit 2 |
21st January 2011 |
the remaining spent nuclear fuel is transported from the V1 NPP |